    India to Add 10 GW Renewable Energy Capacity in 2022

    India is estimated to add about 10 gigawatt (GW) of total renewable energy capacity in 2022, down 10 per cent year-on-year, according to clean energy consultancy firm Bridge to India.

    “Capacity addition prospects would depend greatly on the timeline for clarity on transmission lines in Rajasthan and Gujarat. Many projects have already got force majeure relief on account of module supply disruption,” it said.

    The consultancy’s early estimates for total capacity addition in 2021 is 11.2 GW, split between utility-scale solar with 7.8 GW, rooftop solar with 1.8 GW, and wind with 1.6 GW, 30 per cent below their projection for the year.

    On basic customs duty (BCD), it added that the distributed solar business, both rooftop solar and open access, would take an immediate hit if it is imposed as expected, from April 2022 onwards.

    “Utility-scale solar projects, already stuck because of the Supreme Court’s transmission order, would also be impacted adversely because of negative cash flow impact,” it said. A final announcement on BCD is expected as part of the Budget release on 1 February 2022.

    According to the firm, the softening process in the module supply chain has already begun. But there is still considerable uncertainty on the power supply situation in China and global demand is expected to pick up with 2022 shipment estimates ranging between 170-220 GW.

    “Any decline would most likely, therefore, be slow and relatively small. We expect mono-PERC module prices to ease off to about $0.25 levels by end of the year,” it added.

    The firm expects bid tariffs for central government offtake projects to stay in the Rs 2.10 to Rs 2.40 range.

    Apart from this, the firm added that clarity on BCD and proposed expansion of the production-linked incentive scheme to cover all bidders would provide a big boost to domestic manufacturing efforts.

    “It would be a major change to see industry nucleus shifting away from project development to manufacturing although we expect only about 8-9 of the 16 bidders to finally go ahead with their proposed plans because of overcapacity and viability, financing concerns,” it said.

    Battery and electrolyser manufacturing schemes are expected to take much longer to take off, added the firm.

    ELE Times Report
    ELE Times Reporthttps://www.eletimes.com/
    ELE Times provides extensive global coverage of Electronics, Technology and the Market. In addition to providing in-depth articles, ELE Times attracts the industry’s largest, qualified and highly engaged audiences, who appreciate our timely, relevant content and popular formats. ELE Times helps you build experience, drive traffic, communicate your contributions to the right audience, generate leads and market your products favourably.

    Technology Articles

    Popular Posts

    Latest News

    Must Read

    ELE Times Top 10